Acquisition Program Baseline (APB)

Woodye2023-03-30  1.3K+

Acquisition Program Baseline (APB)

Acquisition program baselines embody the cost, schedule, and performance objectives for the program. The APB is approved by the milestone decision authority milestone reviews as follows:

  • ConceptBaseline, approved at Milestone I, applied to the effort in Phase I, Demonstration and 
  • DevelopmentBaseline, approved at Milestone II,  is applied  to  the  effort  in Phase II, Engineering and Manufacturing 
  • Production Baseline,  approved  at  Milestone  III,  is applied  to  the  effort  in Phase III, Production and 

 

Each baseline must contain objectives for key cost, schedule, and performance parameters. Objectives are accompanied by minimum requirements called thresholds. Once signed by the milestone decision authority, APBs may only be changed at subsequent milestone or program reviews, or with the approval  of the milestone decision authority as a response to  an unrecoverable baseline deviation.

【友情提示】
(1)请先注册登录后再下载附件。
(2)请使用电脑PC/Mac桌面浏览器下载附件,以获得最佳兼容性。推荐使用Chrome。
(3)如使用手机/平板自带浏览器访问, 请先下载、然后在本机存储中打开文件,附件不支持在线预览、显示或播放。

转载请注明原文地址:https://airmango.net/civil_aviation_words/2470.html
00